Shipboard Aviation Systems

Abstract

CV Launch & Recovery System - This Navy unique project addresses the System Development and Demonstration (SDD) of all systems required to recover and launch Navy/Marine Corps Aircraft (Fixed/Rotary Wing and Vertical/Short Take Off and Landing) operating aboard aircraft carriers, amphibious assault ships and air capable ships. This program element includes the following: (1) Advanced Arresting Gear (AAG) (2) Aircraft Launch & Recovery Equipment Modernization (3) Aircraft Launch and Recovery Equipment Service Life Management program This program is funded under SYSTEM DEVELOPMENT AND DEMONSTRATION because it includes those projects that have passed Milestone B approval and are conducting engineering and manufacturing development tasks aimed at meeting validated requirement prior to full-rate production decision.

Open PDF

Document Details

Document Type
R2 Budgetary Justification
Publication Date
Oct 01, 2018
Source ID
0604512N_5_1319_PB_2018
Change Summary Explanation
Cost/Summary: FY 2018 increased $132.046 million for Advanced Arresting Gear (AAG) System Development and Demonstration (SDD) Completion to support SDD delays resulting from technical failures during test and for revised requirements and program executability to complete remaining aircraft recovery bulletins (ARB)s for the entire air wing to support CVN 78's Initial Operational Test and Evaluation (IOT&E) period. Schedule: AAG: Updated the AAG schedule to move Milestone C from 3rd quarter FY 2018 to 4th quarter FY 2020; SDD end date moved from 4th quarter FY 2017 to 4th quarter FY2020; Technical Readiness Review 3 (TRR3) moved from 1st quarter FY 2016 to 4th quarter FY 2016; Independent Logistics Assessment (ILA) moved from 4th quarter FY 2017 to 2nd quarter FY 2020; Jet Car Test Site (JCTS) Test end date moved from 2nd quarter FY 2017 to 2nd quarter FY 2019; Environmental Qualification Testing (EQT) end date moved from 3rd quarter FY 2016 to 3rd quarter FY 2020; Runway Arrested Landing Site (RALS) testing end date moved from 4th quarter FY 2017 to 1st quarter FY 2020; Shipboard Test end date moved from 1st quarter FY 2019 to 4th quarter FY 2019; Integrated Test & Evaluation (IT&E) start date moved from 1st quarter FY 2017 to 4th quarter FY 2018 and the end date moved to 4th quarter FY 2022; Jet Car Test Site (JCTS) Technical Evaluation moved from 2nd quarter FY 2017 to 2nd quarter FY 2019; Runway Arrested Landing Site (RALS) Technical Evaluation moved from 1st quarter FY 2018 to 1st quarter FY 2020. Technical: Not applicable
Service Agency Name
Navy

Entities

Organizations

  • United States Navy

Tags

Communities of Interest

  • Air Platforms
  • Cyber

DTIC Thesaurus Topics

  • Air Capable Ships
  • Aircraft Carriers
  • Aircrafts
  • Amphibious Assault Ships
  • Amphibious Operations
  • Arresting Gear
  • Contracts
  • Cost Analysis
  • Flight Decks
  • Marine Corps
  • Marine Corps Aircraft
  • Navy
  • Performance Tests
  • Ships
  • Software Development
  • Test And Evaluation
  • Test Facilities

Readers

  • Aerospace Engineering
  • Defense Acquisition Program Management
  • Military Science and Technology Research and Modernization.

Related Documents