Shipboard Aviation Systems

Abstract

CV Launch & Recover System - This Navy unique project addresses the System Development and Demonstration (SDD) of systems required to recover and launch Navy/Marine Corps Aircraft (Fixed/Rotary Wing and Vertical/Short Take Off and Landing) operating aboard aircraft carriers, amphibious assault ships, and air capable ships. This program element includes the following: (1) Aircraft Launch & Recovery Equipment Modernization (2) Aircraft Launch and Recovery Equipment Service Life Management program This program is funded under SYSTEM DEVELOPMENT AND DEMONSTRATION because it includes those projects that have passed Milestone B approval and are conducting engineering and manufacturing development tasks aimed at meeting validated requirement prior to full-rate production decision.

Open PDF

Document Details

Document Type
R2 Budgetary Justification
Publication Date
Oct 01, 2025
Source ID
0604512N_5_1319_PB_2025
Change Summary Explanation
Funding: FY 2023 Reprogramming and FY 2025 Program decreases are due to current execution of the Advanced Recovery Control (ARC) Block Upgrade program. Schedule: ARC Systems Development: Milestone Decision B start and end date moved from Q2 2023 to Q4 2023. Milestone Decision C start and end date moved from Q4 2026 to Q2 2027. ARC Development end date moved from Q4 2026 to Q2 2027. Test & Evaluation for ARC Block Upgrade Testing start date moved from Q3 2025 to Q2 2026 and end date moved from Q4 2028 to Q4 2029. Technical: N/A
Service Agency Name
Navy

Entities

Organizations

  • United States Navy

Tags

Readers

  • Aerospace Engineering

Related Documents