SUPER-POWER KLYSTRON TUBE-TEST FACILITY
Abstract
During this quarter, equipment installation and interconnection was completed with the exception of the crowbar. The interim modulator tests were completed, and the modulator was delivered and interconnected with the remainder of the system. All system interconnection wiring and piping were completed and tested. The beam supply tests were completed into a dc dummy load and this portion of the system performed satisfactorily. The bias supply, resistors, bushings and covers associated with the klystron/modulator tank were installed and tested. The crowbar fabrication was completed and preliminary tests are being conducted.
Document Details
- Document Type
- Technical Report
- Publication Date
- Mar 01, 1963
- Accession Number
- AD0404708
Entities
People
- R. L. Blessing