Some minor modifications were made to the electroding equipment, the winding equipment and the terminating machine. Short runs were first made with the equipment for calibration and adjustment. The ceramic tape required for the pilot run was made in a series of runs on the sheet forming machine. Sample units were made from each run to test the electrical and physical properties of the tape as a matter of control. The pilot run was started. (Author)