PRODUCTION ENGINEERING MEASURE FOR TYPE FW-202 BARRIER GRID STORAGE TUBE.

Abstract

Five barrier grid tubes were assembled and exhausted. The first tube, serial no. 1001, was tested and had normal operation, for beam current and repeater and cancellation tests. The five tubes manufactured exhibited poor beam current characteristics. Target bonding processing and assembly problems were overcome. (Author)