PRODUCTION ENGINEERING MEASURE TO INCREASE THE RELIABILITY OF THE TRANSISTOR TYPE 2N2034.
Abstract
For tasks 1, 2, 4 and 5, process improvements have been made and new procedures have been established. Initial data obtained confirmed the choices in Tasks 4 and 5. Additional test data is required to substantiate the choices in Task 1 and 2. Task 7 is considered to be more than 50% complete. Because of the problems encountered in scribing in Task 3, a new equipment is being procured. While Task 6 had not been started during this quarter, dry boxes had been used on the PEM pilot line. A detailed discussion of the work on the process improvements is reported, and the work on reliability evaluation is also reported. (Author)