Four equipment configurations were tested as follows to evaluate equipment compatibility. The Flatbed Trailer was positioned facing the aft end of the T/E, the ECU was loaded and the ducting was connected between the ACU and the T/E during the first configuration. In the second configuration the aft end of the trailer was positioned to the aft end of the T/E, the ACU was loaded, and the ducting was connected. The Flatbed Trailer was positioned perpendicular to the T/E axis and the ducts connected to the SSCBM ports. The Flatbed Trailer/ACU was connected to the Escort Vehicle pintle hook during the final configuration. The air flow to the T/E was not adversely affected by the ECP 51 hardware and no safety hazards were encountered. (Author)
Document Details
- Document Type
- Technical Report
- Publication Date
- Jun 29, 1964
- Accession Number
- AD0442014
Entities
People
- D. M. Raulston
Organizations
- Boeing