ULTRASONIC WELDING PROCESS AND EQUIPMENT FOR CONSTRUCTION OF ELECTRON- TUBE MOUNTS
Abstract
Fabrication of redesigned tooling for use with the 600watt welder was completed. Satisfactory performance was established during the fabrication of 36 sub-assemblies, and a complete 6080WB electron-tube mount was obtained using the new tooling and a modified assembly sequence. The welder with tooling was then redelivered to Tung-Sol, and operator training was initiated. Also, a precision fixture for crimping stem leads was designed and fabricated. Components welding has been delayed by the effort required for the redesign of tooling. However, design studies of a 600-watt welder with special low clamping forces for welding frame grids have been initiated.