PRODUCTION ENGINEERING MEASURE FOR TYPE FW-202 BARRIER GRID STORAGE TUBE.

Abstract

The pilot production phase of the program was completed. Sixty-nine barrier grid tubes passed complete specification testing and were placed in stock. The low beam current problem was resolved and the single beaded barrier grid gun is now a standard, reliable assembly. The major cause of reject tubes remains defective targets. Although the situation was somewhat improved during this quarter, some further work is still needed in this area, if tube yields above the current 35% to 40% are to be realized. (Author)

Document Details

Document Type
Technical Report
Publication Date
Mar 31, 1965
Accession Number
AD0633734

Entities

People

  • J. D. Hagen

Tags

DTIC Thesaurus Topics

  • Assembly
  • Engineering
  • Manufacturing
  • Mass Production
  • Production
  • Production Engineering
  • Production Management Methods
  • Productivity
  • Specifications
  • Standards
  • Storage Tubes

Readers

  • Electronics Engineering
  • Software Engineering