PRODUCTION ENGINEERING MEASURE TO IMPROVE PRODUCTION TECHNIQUES AND INCREASE THE RELIABILITY OF THE SCL7004/21 AND SCL7004/22 TRANSISTORS.
Abstract
State-of-the-art SCL-7004/21 and SCL-7004/22 samples were supplied; a management plan--Critical Path Plan (Gantt Modified) was submitted and the initial milestone tests were initiated for SCL-7004/21 type devices. Of the seven process improvements, three are being finalized; one is in the state of continuous improvement, two are being initiated and one is scheduled to start March 1, 1966. During this quarter, the Milestone I operating live test was 80% completed and the storage life test 90% completed. The results will be presented in the next quarterly report. (Author)
Document Details
- Document Type
- Technical Report
- Publication Date
- Feb 28, 1966
- Accession Number
- AD0633783