THE NOL 3 MEGAWATT ARC TUNNEL.

Abstract

The construction and installation of the tunnel was completed. The report describes in detail the mechanical, electrical, and instrumentation features of the tunnel. Emphasis is placed on those aspects that are unique for a true temperature hypersonic wind tunnel installation. Special data acquisition instrumentation is described. The tunnel operational regime covers Mach numbers from 4.5 to 11 at supply air pressures from 10 to 68 atmospheres and stagnation temperatures from 2000 to 6000K. Unit Reynolds numbers range from 3000 to 2,000,000 per foot. Results of tunnel shakedown and limited calibration tests are discussed. It was found that all components perform quite well and that tunnel conditions are reproducible with good accuracy. (Author)

Document Details

Document Type
Technical Report
Publication Date
Sep 01, 1966
Accession Number
AD0644509

Entities

People

  • E. M. Winkler
  • G. E. Baum
  • Lance Kaplan
  • M. I. Schlesinger
  • R. L. Humphrey

Organizations

  • Naval Ordnance Laboratory

Tags

DTIC Thesaurus Topics

  • Accuracy
  • Acquisition
  • Air Pressure
  • Atmospheres
  • Calibration
  • Construction
  • Data Acquisition
  • Hypersonic Wind Tunnels
  • Instrumentation
  • Mach Number
  • Measuring Instruments
  • Reynolds Number
  • Stagnation Temperature
  • Wind Tunnels

Fields of Study

  • Physics

Readers

  • Fluid Dynamics.
  • Systems Analysis and Design

Technology Areas

  • Hypersonics
  • Hypersonics - Hypersonic Flow