MH-1A FLOATING NUCLEAR POWER PLANT, REPORT ON FINAL TRIALS TESTING. DESCRIPTION OF TESTS PERFORMED PRIOR TO AND DURING INITIAL START-UP.

Abstract

The MH-1A Floating Nuclear Power Plant was at Fort Belvoir from April 1967 to July 1968 for operational testing to demonstrate acceptability under the construction contract. The purpose of the report is to verify that the testing and operations performed by the contractor and the Government has proven the design and operational procedures of the MH-1A to be safe for continued operation.