Forecast of Schedule/Cost Status Utilizing Cost Performance Reports of the Cost/Schedule Control Systems Criteria: A Bayesian Approach.
Abstract
The report presents a Bayesian approach to a forecasting technique useful in projecting the future cost and schedule of work breakdown structure (WBS) items in Department of Defense contracts. The technique utilizes the data supplied in the cost performance reports (CPR) of the cost/schedule control systems criteria (C/SCSC). The forecast data are invaluable to the project manager supervising the contract, who might thereby avert costly schedule/cost program overruns. The advantages of this method are discussed in the present report and a solved example is hereby given.