CMP Instructions, Specifications, and Example.
Abstract
The problem was to develop a construction scheduling model for the Army Functional Component System (AFCS) which could be used by engineers in the field, theater-of-operation planners, and base development planners. To fulfill this requirement a Facility Scheduling Model and an Installation Tabulation Model were developed. Also included are instructions for architects and engineers and an example of the model. The Installation Tabulation Model duration was compared with duration derived by the CERL Construction Management Procedure (CMP) Computer Simulation Model. The comparison results in a recommended 1.35 multiplication factor for the Installation Tabulation Model. (Author)