PRELIMINARY TEST PROCEDURES FOR TESTING XSM-65A MISSILE PROPULSION SYSTEM INSTALLATION 7-20001.
Abstract
This Test Procedure provides test equipment operating instructions required to perform post-installation operational acceptance tests of the Missile propulsion system. The test procedure is divided into two parts: (1) Integrated component operation test, (2) Propulsion system sequence operation test. Part 1 must be successfully completed before beginning Part 2, and the checkout operations must follow in the order given in this procedure. (Author)