Cost Overrun Optimism: Fact or Fiction
Abstract
The purpose of this study was to determine if the overruns at completion projected by contractor and government personnel are unrealistically optimistic. Research has established that, once a contract is 15 percent complete, the final cost overrun will exceed the cost overrun to date (W. Abba,personal communication, 1992; Christensen, 1989; Heise, 1991; Wilson,1991). Thus, a projected overrun at completion is defined as unrealistically optimistic if it is less than the present cost overrun.
Document Details
- Document Type
- Technical Report
- Publication Date
- Feb 29, 2016
- Accession Number
- AD1007905
Entities
People
- David D. Christensen
Organizations
- Defense Acquisition University