Analysis of Production Lead Time for Missile Repair Parts: Contracts Dealing with Cable Assemblies and Wiring Harnesses
Abstract
This investigation was undertaken to help in the development of a mathematical model for predicting production lead time on missile repair parts contracts dealing with cable assemblies and wiring harnesses. Techniques of regression analysis and graphical analysis were employed on the data observations from thirty cable assembly and wiring harness contracts.
Document Details
- Document Type
- Technical Report
- Publication Date
- Apr 01, 1975
- Accession Number
- ADA009177