ELF Communications SEAFARER Program. Site Survey, Michigan Region. Antenna Construction Cost Factors and Installation Plan.
Abstract
A study of the methods and costs associated with the installation of the underground antenna cable portion of the SEAFARER Project is described. This study included a physical examination of the proposed installation site located in portions of the Upper Peninsula of Michigan. Final installation plans and costs will be determined when system design has been completed. The baseline data contained in the report will be extrapolated as required to support final costing. (Author)