National Program for Inspection of Non-Federal Dams. Sebec Dam ME 00163, Penobscot River Basin, Sebec, Maine. Phase I Inspection Report.

Abstract

The dam is about 276 ft. long with a height of 16 ft. The dam is considered to be in fair condition. Continued spalling and erosion of the gate structure concrete could eventually compromise its structural stability. It is large in size with a hazard classification of significant. It is recommended that the owner engage a qualified engineer to further assess the spalled and eroded concrete of the old power station and fishway. (Author)

Open PDF

Document Details

Document Type
Technical Report
Publication Date
Jun 01, 1981
Accession Number
ADA155796

Entities

Organizations

  • New England District, U.S. Army Corps of Engineers

Tags

Communities of Interest

  • Energy and Power Technologies

DTIC Thesaurus Topics

  • Classification
  • Computations
  • Concrete
  • Construction
  • Dams
  • Drainage Basins
  • Elevation
  • Engineering
  • Engineers
  • Flood Control
  • Intellectual Property
  • Ions
  • Massachusetts
  • Network Protocols
  • New England
  • United States
  • Visual Inspection

Readers

  • Hydraulic Engineering.