Public Works Center Pearl Harbor Fleet Moorings Underwater Inspection Report.
Abstract
During the period 3 through 13 May 1983, a CHESNAVFACENGCOM Engineer-in-Charge and divers from Underwater Construction Team Two (UCT TWO) conducted an inspection of the 42 fleet moorings operated and maintained by PWC Pearl Harbor. Eighteen of the moorings were found to be in good condition, three should not be used due to major discrepancies, and twenty-one were found to be in satisfactory condition for continued use within the constraints of their load capacities. Keywords: Mooring inspection, Underwater inspection, Fleet moorings.
Document Details
- Document Type
- Technical Report
- Publication Date
- Sep 01, 1983
- Accession Number
- ADA167247
Entities
Organizations
- Naval Facilities Engineering Systems Command