Santa Ana River Design Memorandum Number 1. Phase 2. GDM on the Santa Ana River Mainstem, Including Santiago Creek. Volume 5. Oak Street Dam
Abstract
The recommended plan for Oak street Drain consists of a concrete channel beginning at the existing Oak Street debris basin and extending over 3 miles to the confluence with Temescal Wash. The channel is designed to provide 100-year level of protection. Total project first cost is estimated at $20,652, 000. The economic data for the project is contained in Volume 9, 'Economics and Public Comment and Response.'
Document Details
- Document Type
- Technical Report
- Publication Date
- Aug 01, 1988
- Accession Number
- ADA204546
Entities
Organizations
- Los Angeles District, U.S. Army Corps of Engineers