The purpose of this environmental assessment is to address the effects of placing approximately 5,000 feet of riprap for bank protection and closing dam construction in Pool 11 of the Upper Mississippi River. Alternative to the proposed action include the No Federal Action alternative, other locations/configurations, and repair of structures without additional riprap bank protection. The project is expected to be beneficial to maintaining the navigation channel, with no significant impacts to natural, cultural, economic, or social resources.
Document Details
- Document Type
- Technical Report
- Publication Date
- Jul 01, 1989
- Accession Number
- ADA219375
Entities
Organizations
- Rock Island District, U.S. Army Corps of Engineers