Rocky Mountain Arsenal, Sections 26 and 25 Contamination Survey. Phase 1
Abstract
This final technical plan describes the work to be undertaken to provide technical services necessary to conduct a phase I survey of sections 26 and 35. The objective of task 6 is to obtain the semiquantitative chemical data from each site sufficient to allow determination of site geometry, contaminants present, and design of the phase II program. Sections of this report detail information on the following: field sampling, geophysical investigation, chemical analysis, and contamination assessment. Appendix a contains a letter technical plan for additional basin F sampling.
Document Details
- Document Type
- Technical Report
- Publication Date
- Dec 01, 1987
- Accession Number
- ADA272310