Proposed Decision Document for the Interim Response Action for the Improvement of the North Boundary System at Rocky Mountain Arsenal Via Construction of Groundwater Recharge Trenches
Abstract
The objective of this interim response action is to correct an hydraulic imbalance in the north boundary treatment and recharge system. Ten gravel filled recharge trenches will be constructed along the down-gradient side of the slurry wall. This proposed decision document provides summaries of: Alternative technologies considered; Significant events leading to the awarding of the IRA contract; The IRA project; and The applicable or relevant and appropriate requirements, standards, criteria, or limitations (ARAR'S) associated with the program.
Document Details
- Document Type
- Technical Report
- Publication Date
- Apr 01, 1988
- Accession Number
- ADA286372