Hydrazine Blending And Storage Facility,
Abstract
The objective of task 11 is to conduct a contamination survey of the soil and ground water in the vicinity of the HBSF that will provide information necessary to assess the nature and extent of contamination. The technical plan has been developed to provide pertinent information for 1) The preparation of an RCRA closure plan, which requires continued ground water monitoring, and technical plan provides recommendations for augmenting the existing monitoring networks along with a description of the proposed field sampling program for task 11. Sections of this plan detail information on the following programs: 1. Field sampling 2. Chemical analysis 3. Quality assurance 4. Data compilation and management. -BKA
Document Details
- Document Type
- Technical Report
- Publication Date
- Mar 01, 1986
- Accession Number
- ADA291459
Entities
Organizations
- Ebasco Services