Alternative Assessment of Interim Response Actions for Other Contamination Sources, M-1 Settling Basins, Version 2.0.
Abstract
This document describes the process and results of the alternatives assessment conducted for the M-1 setting basins. These three basins are located in the south plants area and appear to be a direct source of as contamination to the ground water. (1) Introduction, (2) Site background and results of current and previous investigations, (3) Identification and evaluation of interim action technologies, (4) Development and evaluation of alternatives, (5) Cost estimates. The preferred alternatives are (1) In-situ vitrification and (2) chemical fixation with on-site disposal.