Reducing DoD Product Development Time: The Role of the Schedule Development Process.
Abstract
According to the Packard Commission, "Unreasonably long acquisition cycles -- ten to fifteen years for major weapon systems is a central problem from which most other acquisition problems stem." Since the commission issued its report in 1986, the time required to develop new military systems has only grown. This research and its recommendations are intended to identify and eliminate the causes of those long development times for military systems. This report addresses a key factor in determining the development time for military projects: the project's initial schedule. Part 1 outlines the current situation, previous efforts to reduce development time, and experiences with cutting development time in the commercial sector. It also documents the military product development process. Part 2 identifies a key area--the schedule development process, and its impact on development time--for in-depth research. Through understanding what is driving the initial project schedule and the impact of the initial project schedule on the eventual development time, the author identifies key drivers of development time. Part 3 presents the results of three surveys and analyzes the processes used to develop a project's initial schedule, the process used to develop a contracted schedule, and the impact of these schedules on actual development time. Part 4 presents observations, draws conclusions, and makes specific recommendations for remedial action.
Document Details
- Document Type
- Technical Report
- Publication Date
- Jun 30, 1999
- Accession Number
- ADA366423
Entities
People
- Ross T. Mcnutt
Organizations
- Air Force Institute of Technology