Draft Work Plan for an Engineering Evaluation/Cost Analysis in Support of the Risk-Based Approach to Remediation at Pumphouse Number 2. Malmstrom Air Force Base, Great Falls, Montana

Abstract

This work plan was prepared by Engineering-Science, Inc. (ES) and describes the scope of work required for the collection and analysis of data to complete an engineering evaluation/cost analysis (EE/CA) in support of a risk-based remediation decision for soil and ground water contaminated with fuel hydrocarbons at Pumphouse #2 at Malmstrom Air Force Base (AFB), Great Falls, Montana. Under the basewide Installation Restoration Program (IRP), Pumphouse #2 is a portion of Site PS-3 and may be referred to as such in referenced documents used in preparation of this work plan. This work plan is the equivalent of a treatability study test design (TSTD) for the field test of the risk-based approach to remediation at Pumphouse #2. This innovative technology is sponsored by the Air Force Center for Environmental Excellence (AFCEE) at Brooks AFB, Texas, under contract F41624-93-C-8044, "Risk-Based Approach to Fuel Spill Remediation." The Pumphouse #2 demonstration is a component of a multi-site initiative being sponsored by AFCEE to demonstrate how quantitative fate and transport calculations and risk information based on site-specific data can be integrated to quickly determine the type and magnitude of remedial action required at a site to minimize contaminant migration and receptor risks.

Open PDF

Document Details

Document Type
Technical Report
Publication Date
Aug 01, 1994
Accession Number
ADA384289

Tags

Communities of Interest

  • Biomedical

DTIC Thesaurus Topics

  • Air Force
  • Alkanes
  • Chemical Synthesis
  • Chemistry
  • Environmental Protection
  • Groundwater
  • Hydrocarbon Fuels
  • Materials Science
  • Organic Chemistry
  • Two Dimensional

Readers

  • Environmental Remediation and Restoration.
  • Systems Analysis and Design