The National Shipbuilding Research Program. Occupational Safety & Health Administration (OSHA) Technical Advisory Committee
Abstract
This Project was begun on 4 June 1998 and was completed on 29 Dec 2000 under NASSCO Purchase Order MU322700-D dated 6 April 1998. Administrative arrangements for processing Subtasks under this Project were developed based on the general requirements for performing projects under the NSRP. The members of the SP-5 Ad Hoc Committee approved these arrangements for Safety & Health and by the NSRP Program Manager at NASSCO. A total of 12 Subtasks Tasks were submitted by the Ad Hoc Committee from which 19 Subtasks were approved and completed on schedule and on or under budget. Final reports were submitted to the program manager.
Document Details
- Document Type
- Technical Report
- Publication Date
- Dec 29, 2000
- Accession Number
- ADA448638
Entities
Organizations
- National Steel and Shipbuilding Company