Defense Acquisitions: Zumwalt-Class Destroyer Program Emblematic of Challenges Facing Navy Shipbuilding

Abstract

DDG 1000 development has been framed by challenging multimission requirements, resultant numerous new technologies, and a cost and schedule budget that added to-rather than eased-the challenge. While the Navy has done much work to try to manage the program within these competing goals, it will begin lead ship construction in October 2008 with significant uncertainties, particularly in developing the ship's design, key components, and the ship software system. Recent restructuring of the schedule buys more time for technology development, but shifts key efforts like installation and testing of the combat systems until later in the construction schedule-after the ships have been initially delivered. Such compromises-made before construction has even begun-suggest that the Navy already has little margin for solving future problems without adding money and time. In fact, it appears that the budget for the lead ships is not adequate to deliver fully operational ships. The complexity and unique features of DDG 1000, along with the design work, testing, and actual construction experience to come, add to the risk of cost growth.

Open PDF

Document Details

Document Type
Technical Report
Publication Date
Jul 31, 2008
Accession Number
ADA484547

Entities

People

  • Paul L. Francis

Organizations

  • United States Government Accountability Office

Tags

Communities of Interest

  • Ground and Sea Platforms

DTIC Thesaurus Topics

  • Acquisition
  • Aircraft Carriers
  • Boats
  • Destroyers
  • Electromagnetic Aircraft Launch Systems
  • Littoral Combat Ships
  • Manufacturing
  • Military Acquisition
  • Naval Warfare
  • Navy
  • Procurement
  • Radar
  • Shipbuilding
  • Ships
  • Software Development
  • United States Government
  • Zumwalt Class

Readers

  • Defense Acquisition Program Management
  • Naval Architecture and Marine Engineering.
  • Systems Analysis and Design