Performance Evaluation of Pre-Cast Slabs for Contingency Rigid Airfield Pavement Damage Repair

Abstract

Draw backs of cast in-place include: a) weather window essential for operations might not be available b) several days of closure. Advantages of Pre-cast include: can be completed in about 6 hours, more control on material properties of the precast concrete, texturizing the surface for tire-pavement interaction. Draw backs of Pre-cast: cost (1.6 to 4 times higher), Transportation of the panels. This study investigates the feasibility and the efficiency of using different precast concrete panel installation techniques. High density polymer (HDP) foam and flowable fill were selected as the leveling materials after literature review. The precast panels were installed using three installation techniques (conventional injection, deep injection and flowable fill) to study their impact on the performance of the repaired sections characterized by load transfer efficiency, joint stiffness and deformation energy dissipated through the pavement foundation.

Open PDF

Document Details

Document Type
Technical Report
Publication Date
Oct 01, 2010
Accession Number
ADA532727

Entities

People

  • Athar Saeed
  • Michael P. Hammons
  • Reza Ashtiani

Organizations

  • Applied Research Associates (United States)

Tags

Communities of Interest

  • Energy and Power Technologies

DTIC Thesaurus Topics

  • Air Force
  • Air Force Facilities
  • Air Force Research Laboratories
  • Bonding
  • Concrete
  • Contracts
  • Deflection
  • Efficiency
  • High Density
  • Leveling
  • Literature Surveys
  • Materials
  • Mechanical Properties
  • Military Research
  • Precast Concrete
  • Stiffness
  • Stresses

Fields of Study

  • Materials science

Readers

  • Electrical Engineering
  • Pavement Materials Engineering.