Defense Management: DOD Has a Rigorous Process to Select Corrosion Prevention Projects, but Would Benefit from Clearer Guidance and Validation of Returns on Investment

Abstract

The acceptance of the military departments' CPC proposals varied relative to the types of projects and nature of review that the military Corrosion Executives required before the proposals were submitted to the Corrosion Office for funding consideration. DOD guidance provides that Corrosion Executives coordinate CPC actions, including submitting corrosion project opportunities. Prior to submitting the proposals for a preliminary evaluation by the Corrosion Office's project selection panel, Army and Navy Corrosion Executives and staffs reviewed proposal summaries and provided feedback to the authors. The Air Force did not perform a review that included presubmission feedback. Later, during a preliminary evaluation, the Corrosion Office's project selection panel determined that a much higher percentage of Army and Navy proposals were acceptable than those submitted by the Air Force. A selection panel member told us that because the Air Force did not perform a pre-submission review of proposals, deficiencies in those proposals were not corrected prior to the panel's evaluation.

Open PDF

Document Details

Document Type
Technical Report
Publication Date
Dec 01, 2010
Accession Number
ADA534381

Entities

Organizations

  • United States Government Accountability Office

Tags

Communities of Interest

  • Ground and Sea Platforms

DTIC Thesaurus Topics

  • Business Administration
  • Cathodic Protection
  • Congress
  • Corrosion
  • Corrosion Inhibition
  • Department Of Defense
  • Electronic Mail
  • Governments
  • Investments
  • Law
  • Materials
  • Military Equipment
  • Military Facilities
  • National Security
  • Test And Evaluation
  • United States
  • United States Government

Readers

  • Clinical Trial Research.
  • Defense Acquisition Program Management
  • Instructional Design and Training Evaluation.