Environmental Assessment: Gulf Power Company Military Point Transmission Line Project
Abstract
Tyndall Air Force Base (AFB) has requested that Gulf Power Company provide additional electrical power to meet future energy demands that are forecasted to exceed available capacity as early as 2004. The purpose of the Proposed Action is to construct a new aerial (i.e., overhead) 46kV transmission line, built to 115kV standards, across St. Andrew Bay to connect with existing electrical infrastructure at Military Point for additional electrical power to the Base.