AGOR 28: SIO Shipyard Representative Bi-Weekly Progress Report
Abstract
Progress on the building of AGOR 28, oceanographic research vessel Sally Ride. Work continues on initial outfitting lists for Sally Ride and NS5 Hierarchy. The yard is working towards providing an up dated test schedule for Ride. The current schedule has obsolete dates that are no longer relevant. There are 137 items on the schedule with 25 to 30 at or near 100% completion. 9 are for BT and AT. The remaining need to be done prior to Builder's Trials.