Case Study: Lockheed and the C-5A
Abstract
A brief summary of the need for the C-5A aircraft by the United States and Lockheed Aircraft Corporation serves as an introduction to a discussion of the reasons behind the cost overrun involved in producing this massive aircraft. Government procurement practices are examined with emphasis placed on the Total Package Procurement Concept and the resulting C-5A contract. The causes of the cost overrun in the areas of contractual obligations, equipment problems, and management inefficiencies are presented along with a discussion of the alleged concealment of the mounting costs. Finally, the lessons learned from the C-5A experience are summarized.
Document Details
- Document Type
- Technical Report
- Publication Date
- Apr 01, 1976
- Accession Number
- ADB011275
Entities
People
- John N. Shults
Organizations
- Air War College