- Document Type
- R2 Budgetary Justification
- Publication Date
- Oct 01, 2024
- Source ID
- 1206444SF_5_3620F_PB_2024
- Change Summary Explanation
- FY 2023: +899.196M; in accordance with Congressional transfer direction in the FY 2023 enacted budget, funds in PE 1206442SF, Project 657121, Next-Gen OPIR Space, Block 0 Polar, have transferred to PE 1206444SF. FY 2023: -90.000M; Congressionally directed reduction for expenditure delays relating to undefinitized contract action. FY 2023: +25.000M; Congressional add for schedule risk reduction. FY 2023: +15.000M; Congressional add for onboard resilience. FY 2024: +1013.478M; in accordance with Congressional transfer direction in the FY 2022 enacted budget, funds in PE 1206442SF, Project 657121, Next-Gen OPIR Space, Block 0 Polar, have transferred to PE 1206444SF and for inflation.
- Service Agency Name
- Air Force