National Dam Safety Program. Hadlock Pond Dam, Inventory Number (NY 625), Lake Champlain Basin, Washington County, New York. Phase 1 Inspection Report

Abstract

This report provides information and analysis on the physical condition of the dam as of the report date. Information and analysis are based on visual inspection of the dam by the performing organization. Hadlock Pond Dam did not reveal conditions which pose an immediate threat to life or property. Additional studies are recommended. Possible embankment overtopping can result from storms exceeding 13% of PMF. Assuming complete breaching of embankment, water surface levels could reach depths posing significant danger to residents. Consequently the spillway is assessed as unsafe non-emergency (SEE REPORT ASSESSMENT). A detailed emergency operation plan, warning system, and surveillance should be implemented as remedial measures are completed. Additional deficiencies were noted.

Open PDF

Document Details

Document Type
Technical Report
Publication Date
Sep 24, 1979
Accession Number
ADA075859

Entities

People

  • George W. Koch

Organizations

  • New York State Department of Environmental Conservation

Tags

Communities of Interest

  • Energy and Power Technologies

DTIC Thesaurus Topics

  • Classification
  • Concrete
  • Construction
  • Dams
  • Department Of State
  • Embankments
  • Engineers
  • Inspection
  • Materials
  • New York
  • Phase
  • Plastic Explosives
  • Precast Concrete
  • Reinforced Concrete
  • Soil Mechanics
  • Visual Inspection
  • Warning Systems

Readers

  • Hydrologic Risk Analysis and Mitigation.