Civil Defense Research Project Annual Progress Report, March 1971 - March 1972
Abstract
With the advent of industrialized housing it becomes apparent that faster methods of utility installation will be required to ensure that occupancy of the housing can proceed as soon as possible. One possible approach that has been suggested is the installation of multiple utilities in the same trench. In this approach excavation is minimized and all utilities are in stalled at the same trench. Limited attempts have been made using common trenches in the United States and it has been found that technical problems are not as important as those involved with coordinated planning, design and installation.
Document Details
- Document Type
- Technical Report
- Publication Date
- Mar 01, 1972
- Accession Number
- ADA382232